City of Batavia - Wastewater Treatment Facility Phased Rehabilitation
The $42.6 Million Phase 2A Rehabilitation project at the City of Batavia's WWTF is nearing completion, several months ahead of schedule and with less than 0.5% in change orders. After completing off-site utility and roadway replacement, bike path realignment, replacement of the process flow disinfection system, and rehabilitation of the final clarifiers, wastewater was completely transferred over to the brand-new Headworks and Primary Clarifiers in October 2025.
This project’s success is a result of the outstanding dedication and collaboration of the General Contractor IHC, the City of Batavia Public Works staff, and our Trotter project representatives. We sincerely thank everyone for making this achievement possible!