
The Village of Barrington Hills has kicked off its 2025 Road Program, which includes HMA resurfacing along three miles of roadway and patching and striping on five miles of various roadways within the Village. With the initial removal completed, crews have begun placing reflective crack control fabric along the milled roadway. Utilization of this fabric on resurfacing projects reduces reflective cracking from the underlying pavement. It acts as a moisture barrier, all of which assist in extending the service life of the roadway. The final HMA surface placement along Spring Creek Road and Buckley Road, patching of various streets, and striping are expected to be completed in the coming months.

The Village of Algonquin, Trotter and Associates, Inc., and Manusos General Contracting are excited to be moving into the construction phase of the WWTF Biosolids Handling Improvements project. With anticipated long lead times for equipment, the project team is working diligently to process submittals to ensure installation of the two decanter centrifuges can begin in the Spring of 2026 as planned. Upon completion of the project, the Village will have met its goal of upgrading the sludge dewatering operation to maintain processing current demands and allow for future development.
Concrete repairs are vital for preserving the integrity of existing structures and enhancing their service life. This was the main objective for the Structural Repairs Project at Fox River Water Reclamation District’s North and West facilities. To meet this objective, the Trotter structural team evaluated numerous buildings, tanks, and components at both facilities to develop a comprehensive repair plan. Repairs ranged from minor crack injection to full-depth concrete repairs, masonry repairs, and improvements to aluminum stairs and guardrails. Dahme Mechanical Industries (DMI) and its team of subcontractors, Manusos General Contracting, Bulley & Andrews, Alliance Concrete Sawing and Drilling, and A. Horn Inc., are wrapping up the final stages of the project. The remaining scope of work includes regrouting a Final Clarifier and extensive rehabilitation of a concrete structure that dates to the early 1950s. In addition to the structural components of this project, existing stop plates at the West Facility’s Chlorine Contact Tank were replaced with slide gates, improving operational efficiencies for District Staff. The DMI team effectively and efficiently installed all fourteen gates within a week, allowing District Staff to resume maintenance on their facilities in preparation for the disinfection season.

The Glenbard Wastewater Authority is currently in the process of rehabilitating and upgrading its primary clarification, sludge pumping, and gravity thickening operations. In late 2024, the 2025 Primary Clarifier Rehabilitation project was bid to replace infrastructure that was reaching the end of its service life, as well as to provide better operational controls for the Authority. This project includes the removal and replacement of both 110-foot clarifier mechanisms and sludge pumping equipment. The new pumps will be on VFD’s to better manage solids within the process and will have the option to be directly fed to the anaerobic digesters. In addition, the existing gravity thickener will have its equipment removed and replaced. The Authority elected to include launder covers on both clarifiers for odor mitigation and the removal and replacement of the gravity thickener dome with a new flat cover. The project also includes upgrades to the existing electrical equipment and SCADA system and the replacement of diversion structure gates. Construction is underway and is anticipated to be completed in early 2026.

In 2022, Trotter and Associates, Inc. completed an assessment of the Village of Algonquin’s Braewood Lift Station. The primary improvements focused on increasing the station’s capacity to handle the rapid growth in both the Braewood Lift Station service area and the upstream Grand Reserve Lift Station service area. With the increased capacity of the station, the velocity through the existing 10-inch force main exceeded allowable limits. To address this, a 16-inch force main was included in the design, which was constructed in 2024. With the force main constructed, the station rehabilitation has commenced. Work within the station includes upsizing the piping and pumps, replacing the grinder, and improving both the electrical and HVAC systems. Upon completion of the work, the pumping capacity of the station will be increased from 1,500 gallons per minute (GPM) to 5,000 GPM, allowing the Village to meet both current and future development demands.

To facilitate IDOT’s proposed widening of Illinois Route 53 at Butterfield Road, Illinois American Water was required to relocate several of its facilities within IDOT’s right-of-way. Illinois American Water retained Trotter and associates to design the relocation of a quarter mile of sanitary sewer, over a mile of water main, and a water pressure reducing station. These utility relocations are expected to begin within the next several months.