PROJECTS

OUR PROJECTS

Trotter and Associates, Inc. (TAI) has developed a handpicked team of professionals who are able to identify sound engineering solutions to unique problems. Our team holds leadership positions in local, regional, and national organizations. We are on the leading edge of best management practices, available funding sources, and regulatory changes. As part of our commitment to the industry, we are continuously investing into the evaluation and implementation of emerging technologies.


TAI’s staff works closely with each client to prioritize their needs, evaluate alternatives, and develop project-specific solutions. Throughout this process, TAI focuses on educating our clients with respect to the advantages of each alternative, as well as the cost. TAI’s clients are able to make informed decisions that meet the communities’ long-term needs.



TAI has completed numerous marquee projects that provide a complete solution including planning, design, funding, and implementation. Below is a sample of projects which have resulted in significant improvements to our communities’ civil infrastructure.

By Mark Dupree July 13, 2026
The Primary Clarifier Improvements Project for the Glenbard Wastewater Authority is officially complete. Trotter and Associates, Inc. provided design and resident engineering services for this rehabilitation project, which upgraded aging treatment equipment while improving operational flexibility and reliability. Major improvements included rehabilitation of the Authority’s two primary clarifiers and gravity thickener with new stainless steel collection mechanisms, replacement of sludge and scum pumps, piping, valves, meters, and associated electric and control systems, replacement of clarifier influent and effluent gates with the addition of electric actuators, replacement of large-diameter clarifier effluent piping in their diversion structure, and installation of new thickened waste activated sludge piping from the gravity thickener to the existing anerobic digesters to allow additional operational control of the primary sludge and thickened waste activated sludge. Additional upgrades focused on improving plant operations and odor mitigation by installing primary clarifier launder covers and a new walkable aluminum flat cover over the gravity thickener. Construction was completed while maintaining continuous plant operations. A 47 MGD temporary bypass system was implemented to facilitate installation of the diversion structure gates and large-diameter clarifier effluent piping, while a temporary solids thickening operation maintained the solids treatment processes during the gravity thickener equipment rehabilitation. Project Team Included: Glenbard Wastewater Authority, Trotter and Associates, Inc., Vissering Construction, Dahme Mechanical Industries, Connelly Electric Co., and TRI-R Systems, Inc. 
By Mark Dupree July 1, 2026
The City of Burlington, WI continues to invest in reliable wastewater infrastructure with planned improvements to the Primary Digester mixing system at its Water Pollution Control Facility. Trotter and Associates provided engineering services for the project, which will replace the existing gas mixing system with a pumped jet mixing system similar to the technology currently operating in the facility's secondary digester. The improvements will support long-term operational reliability and treatment performance. The project went out to bid in January and was awarded to Rohde Brothers, Inc. Construction is planned for the Fall of 2026. 
By Mark Dupree May 31, 2026
Fox Metro Water Reclamation District is nearing completion of a valve replacement project for the pumps serving the 54" Primary Clarifier Effluent (PCE) and 42" Return Activated Sludge (RAS) force mains. The hydraulically operated plug valves, originally installed in the 1970s, are being replaced with conventional plug/check valve arrangements, along with surge and air-release valves where required. To date, Dahme Mechanical Industries has completed valve installations on all three RAS pumps and three of the four PCE pumps, with the final pump expected to be completed in the coming weeks. Before the mechanical work, a floor shoring system was installed to reinforce a portion of the elevated slab and properly support the new valves. TAI's involvement in this project has spanned from the early planning stages, including structural condition verification, pump system curve analysis, and surge analysis, through the preparation of bidding documents, and now into active construction support. 
By Mark Dupree May 1, 2026
The City of St. Charles is nearing completion of phase one of the Well No. 8 Water Treatment Plant (WTP) Rehabilitation Project, which includes upgrades to piping, valves, and treatment systems—specifically ion exchange and HMO filtration processes that support radium removal and hardness control. These improvements build on the City’s already high-performing water system and help maintain consistent water quality. Phase two will begin this fall and will include installation and commissioning of the Well No. 14 pump, replacement of the pump at Well No. 8, and electrical and other minor facility upgrades to WTP No. 8. Once complete, these enhancements will increase the available water supply, improve operational flexibility, and strengthen long-term system reliability for the community. 
By Mark Dupree March 27, 2026
The Village of Addison is implementing a major project to separate combined sewers in the Home Addition area, which is the largest remaining combined sewer tributary in the community. The project includes separating the area's existing combined sewer system, which currently manages both wastewater and stormwater runoff, into separate sanitary and storm sewer systems. About three miles of new storm sewer, ranging from twelve to sixty inches in diameter, will be installed and directed to Salt Creek through an existing 84-inch relief storm sewer. To connect to the existing 20-foot-deep relief sewer, two custom-made junction chambers (10-foot by 12-foot and 8-foot by 10-foot) have been installed. Another key part of the project is building a stormwater detention facility at Cherokee Park, which is the lowest point of the drainage basin and the area most vulnerable to flooding. Since June of 2025, the contractor has completed approximately two and a half miles of storm sewer installation. The remaining sewer work and excavation of the detention pond are expected to be finished in the coming months. Along with storm sewer upgrades, lead water services found during construction are being replaced. So far, 65 lead water services have been taken out of the Village's water system. Once finished, the Village’s sanitary sewer system will experience significantly lower flows during wet weather. This decrease in flows will help prevent basement backups, street flooding, and combined sewer overflow discharges previously suffered by the Village. The project will also lessen the volume of stormwater runoff treated at the AJL Wastewater Treatment Plant. It remains on schedule and is expected to be completed by summer 2026. 
By Mark Dupree March 23, 2026
Phase 2 of the Village of Fox Lake's Lead Service Line Replacement Program is nearing completion. This program aligns with the 2024 updates to the EPA's Lead and Copper rules, which require water providers to begin replacing lead and galvanized water service lines. The original water system in the project areas dates back to 1929, when lead water services were common. To comply with regulations, all lead and galvanized water services are being replaced from the water main to the customer's meter inside the house. Both phases of this program are funded through the IEPA's Public Water Supply Loan Program, in which the Village has received principal forgiveness for the entire $5.1 million loan. To date, the program has replaced approximately 350 water services, and Phase 2 is expected to be completed by June 2026. 
View More

GET IN TOUCH
HAVE AN ENGINEERING PROBLEM THAT YOU'D LIKE OUR HELP WITH?