By Mark Dupree 09 Jun, 2022
The City of St. Charles owns and operates a sanitary sewer collection system and two wastewater treatment facilities: The Main Wastewater Treatment Facility and the West Side Water Reclamation Facility. The collection system tributary to the Main Wastewater Treatment Facility (Main WWTF) consists of approximately 152 miles of sanitary sewers, 5 miles of force main and 13 lift stations. The Main WWTF is located at the Public Works Facility, 1405 S. 7th Avenue on the eastern shore of the Fox River. The treatment facility has a design average treatment capacity of 9 million gallons per day (MGD). The facility generally serves the community’s wastewater needs east of Randall Road and discharges to the Fox River. The facility provides preliminary, primary, and secondary treatment for flows received from the tributary communities to meet strict effluent water quality requirements before discharging to the Fox River. The St. Charles Main WWTF was required to comply with a 1 mg/L phosphorus limit. It was likely that the treatment facility will need to achieve lower phosphorus effluent limits prior to 2030. Trotter and Associates completed the Facility Plan and Phosphorus Removal Feasibility Study in 2015. The analysis utilized BioWin™ to evaluate various treatment methods and technologies. The selected alternative was an A 2 O process to address the phosphorus limit and future Total Nitrogen requirements. The recommendations also included construction of a chemical feed system for polishing, a chemical buffering system for struvite prevention, and a primary sludge fermenter for enhanced BPR. The 2015 Facility Plan also identified the need for a Digester Improvements project. The existing anaerobic digesters were constructed in 1989. The previous digested sludge storage tank was constructed in 1951 and repurposed multiple times. The Facility Plan recommended rehabilitation of the anaerobic digesters and replacement of the digested sludge storage tank. It was further recommended that the project be completed jointly with the Phosphorus Removal Project to expedite the completion schedule and minimize disruption to treatment facility operations.
2014 Facility Plan and Phosphorus Removal Feasibility Study
By Mark Dupree 04 May, 2022
The City of Batavia owns and operates a 4.2 MGD conventional activated sludge wastewater treatment facility. The plant was originally constructed in 1935 and has been expanded numerous times over the life of the facility. Scott Trotter has worked with the City of Batavia on wastewater projects since 1990. In 2008, TAI completed a Wastewater Master Plan Update that outlined the City’s short and long term needs with respect to expansion, rehabilitation and regulatory upgrades. In 2012, TAI updated the plan and evaluated emerging technologies and alternative conventional processes to meet the City’s needs. Previous reports had established that expansion was necessary, and therefore the plant would need to remove total nitrogen due to anti-degradation requirements. Numerous configurations were considered for BNR including A 2 O, Bardenpho, UCT and MLE processes. The City of Batavia’s treatment facility is “land locked” and the detention time required to achieve BNR within the existing tankage prompted the team to analyze Integrated Fixed Film Activated Sludge (IFAS) and lysis technologies to reduce footprint and sludge production. In 2014, the City elected to pursue acquisition of additional property and move forward with a conventional 5-Stage Bardenpho process due to its robust nature and ability to meet future limits. During the due diligence, the Illinois EPA and the Fox River Study Group (FRSG) arrived at consensus with respect to NPDES permit language regarding future nutrient limits. The permit language requires POTW’s to complete a Phosphorus Removal Feasibility Study for meeting permit limits of 1.0 and 0.5 mg/L total phosphorus (TP) as well as design and construction of the necessary improvements for 1.0 mg/L within 54 months. Due to the compliance schedule and other issues identified during due diligence, the City determined that land acquisition was not practical and directed TAI to proceed with design of the on-site alternative. The proposed design will allow for construction in phases. Phase I includes Chem-P to meet the interim 1 mg/L TP standard, and this project was completed in 2019. Phase II will incorporate a 5-Stage Bardenpho process for biological nutrient removal.  TAI also completed the Phosphorus Removal Feasibility Study. Previous reports had provided a thorough analysis of BNR technologies and selected the 5-Stage Bardenpho Process. This work was incorporated into the study with respect to the Present Worth Analysis. However, due to the dates within the compliance schedule, the City implemented Chem-P during Phase I. TAI worked with the City and Suburban Laboratories to complete jar testing and determine the chemical dosage requirements necessary for meeting the 1.0 mg/L and 0.5 mg/L TP limits. The report also included conceptual design of five alternative biological process layouts for the ultimate design and layout of the facility. These designs were thoroughly vetted with a 3rd party review prior to making recommendations to the City and submitting the Facility Plan and Feasibility Study. The alternative recommended by this process and accepted by the City was a deep-basin design for the expanded biological process. This design was included in the Facility Plan Update and Phosphorus Removal Feasibility Study, which were both submitted in 2014.
By m.dupree 09 Aug, 2017
The City of North Chicago has over 340,875 linear feet (over 64.5 miles) of roads and alleys to maintain. Totaling over 8,408,666...
By m.dupree 09 Aug, 2017
The Fox Lake Water Department was struggling to identify all existing taxing boundaries within the community and wanted to ensure that the...
By m.dupree 09 Aug, 2017
The City of Harvard had an existing AutoCAD data file that included their water system distribution map and an AutoCAD file with...
By m.dupree 09 Aug, 2017
Trotter and Associates, Inc. (TAI) cleaned and optimized all of Algonquin Township’s spatial data (Esri, AutoCAD, PDF and JPG) on the Township...
View More

GET IN TOUCH
HAVE AN ENGINEERING PROBLEM THAT YOU'D LIKE OUR HELP WITH?

Share by: