DeKalb Sanitary District – Country Club Lift Station Improvements

Jun 29, 2017

TAI provided planning, design, and construction phase engineering services related to the replacement of a regional lift station on Buena Vista Golf Course (DeKalb Park District) for the DeKalb Sanitary District. The project included the construction of a new cast-in-place wet well and valve room structure with a brick and block building which houses the electrical/control room and generator room. The lift station was designed for phased expansion to meet the community’s long-term needs and includes room for four VFD controlled submersible pumps. The first phase included two submersible pumps, magnetic flow meter, SCADA communication, and back-up generator.

The project was funded through the ARRA program.  The improvements were substantially completed in December 2010 and final restoration was completed in April 2011.

2011 APWA Environmental Project of the Year (Under $5 Million)